The four German transmission system operators 50Hertz, Amprion, TenneT and TransnetBW published the preliminary grid fees for 2027 on October 1, 2026. At the extra-high voltage and transformation levels, the average fee rises from 2.86 to 3.54 cents per kilowatt-hour because the federal subsidy falls by just under one billion euros. For plant management, energy management and executive leadership in manufacturing, the supplier industry and intralogistics, this lands right in the middle of the budget cycle: the distribution system operators, whose grids most plants are connected to, will publish their price sheets for 2027 in the coming weeks. Even before then, you can determine how strongly your site depends on its most expensive quarter-hour of the year.
The preliminary grid fees for 2027 On average, transmission-level rates will be about 24 percent higher than in 2026, while power prices for consumption points with fewer than 2,500 hours of use will rise by about 30 percent. These figures will not be final until the subsidy is enacted into law; otherwise, they will be higher after December 7, 2026. It is certain that costs will rise. For most industrial sites, the key decision is therefore whether individual load peaks will determine the capacity price for the entire year. Those who analyze their load profile over the past twelve months can take countermeasures before the end of the year: through organizational measures, automatic peak load capping, or an individualized grid fee.
| Grid level and utilization period | Capacity charge 2026 → 2027 (€/kW per year) | Energy charge 2026 → 2027 (ct/kWh) |
|---|---|---|
| Extra-high voltage, less than 2,500 h/a | 11.39 → 14.78 (+30 %) | 2.36 → 2.81 (+19 %) |
| Extra-high voltage, 2,500 h/a and above | 53.06 → 59.91 (+13 %) | 0.69 → 1.00 (+45 %) |
| Transformation extra-high/high voltage, less than 2,500 h/a | 17.18 → 22.34 (+30 %) | 2.81 → 3.38 (+20 %) |
| Transformation extra-high/high voltage, 2,500 h/a and above | 76.70 → 89.96 (+17 %) | 0.43 → 0.67 (+56 %) |
What the transmission system operators have published
These preliminary figures are based on a subsidy of 5.525 billion euros from the Climate and Transformation Fund, which the Federal Cabinet approved in early September and which is to be enshrined in the new Section 24d of the Energy Industry Act (EnWG). For 2026, the subsidy amounted to 6.5 billion euros. Without it, the average transmission grid fee would rise to 6.52 cents per kilowatt-hour in 2027, according to the grid operators (Press Release from the Transmission System Operators, Oct. 1, 2026). The law has not yet been enacted. If legal certainty is not established by December 7, 2026, the final fees will increase accordingly (Preliminary Price List 2027).
Only a few very large customers pay these prices directly. For high- or medium-voltage facilities, these prices are factored into the distribution system operator’s rates through the costs of the upstream grid. The extent to which this occurs varies by region and will only become clear once the distribution system operators publish their preliminary rate schedules in October (ene’t, Oct. 1, 2026). The fees will take effect on January 1, 2027.
This is how much the average grid fee at the extra-high voltage and transformation levels rises from 2026 to 2027, from 2.86 to 3.54 cents per kilowatt-hour, assuming the federal subsidy is enacted.
Transmission system operators, 10/2026
What the Higher Grid Fees Mean for Your Location
The grid fee for a consumption point with demand metering is the sum of two products: the highest demand of the year times the capacity charge, plus the energy drawn times the energy charge. The highest measured quarter-hour is decisive. Whether the prices in the column below or from 2,500 hours of use apply follows from annual energy divided by this peak load. For plants running two or three shifts, the column from 2,500 hours almost always applies, and there the capacity charge dominates.
A sample calculation using the 2026 rate schedule of an East German distribution system operator, medium voltage starting at 2,500 hours: 116.12 euros per kilowatt per year and 0.67 cents per kilowatt-hour (MITNETZ STROM, price sheet 2026). A supplier plant with an annual consumption of 15 gigawatt-hours and an annual peak load of 3,000 kilowatts thus pays around 348,000 euros for capacity and around 100,500 euros for energy. More than three quarters of the grid fee therefore depend on a single quarter-hour. If the normal peak load is 2,700 kilowatts and the remaining 300 kilowatts only occur because compressors, a hardening furnace and the hall heating start up simultaneously after a maintenance weekend, this one quarter-hour costs around 34,800 euros per year. Every 10 percent increase in the capacity charge adds around 3,500 euros more.
Options to Counter Higher Grid Fees Until the End of the Year
| Option | Effort | Costs | Risk |
|---|---|---|---|
| Do nothing | None | Additional costs equal to the price increase charged by the distribution network operator | An unplanned spike determines the costs for the entire year |
| Analyze load profiles, define startup sequences | A few days | Low | This only works as long as the rules for shift work are followed |
| Automatic peak load curtailment via an energy management system | A few weeks | Medium | Consumers that can be shut off must be clearly defined; otherwise, the process will suffer |
| Atypical Grid Usage Pursuant to Section 19(2) of the StromNEV | Agreement with the network operator, annually | Low to moderate | According to the Federal Network Agency's plans, the regulation is set to expire at the end of 2028 |
| Battery Storage for Peak Shaving | Months | High | Profitability Depends on the Grid Tariff Reform Starting in 2029 |
Atypical grid usage requires that the peak load during the grid operator’s peak load period be significantly below the annual peak load and that at least 100 kilowatts of load shifting be demonstrated (vbw, Guide to Electricity Storage Systems, 09/2025). Each grid operator publishes its own peak-load time windows. Only an analysis of the quarter-hourly values can show whether a given load profile fits within these windows.
Which measure is best suited for which load profile
If the peaks result from startup procedures, shift changes, or material handling vehicles charging simultaneously, fixed startup sequences and automatic curtailment of certain loads (such as refrigeration, compressed air replenishment, or heating coils) are usually sufficient. This is the quickest solution because it requires no investment in generation or storage. If a plant’s load can be scheduled to fall outside peak load time windows (for example, in processes that are concentrated during the night shift) it is worth exploring an individual grid tariff, with an eye toward the announced end date of 2028. Battery storage, on the other hand, rarely pays for itself through peak shaving alone: As part of its AgNes reform, the Federal Network Agency will work with a contracted capacity per grid connection starting in 2029. Band load control and atypical grid usage are set to phase out with the StromNEV at the end of 2028 (Federal Network Agency, Guidelines for Industrial Grid Fees, 04/2026). Anyone investing today should therefore design the storage system to serve multiple purposes.
Grid Fee Check for Your LocationYou send us the quarter-hourly readings for your consumption point from the past twelve months, as provided by your grid operator or metering point operator. Within ten business days, you’ll receive the ten most expensive peak loads with their times and probable causes, the invoice with your 2026 price sheet and, as soon as it’s published, the 2027 price sheet, as well as a list of consumers who can be automatically curtailed. Initial consultation: 30 minutes, free of charge, response within one business day.
Frequently Asked Questions
Do the higher grid fees also apply to medium-voltage facilities?
Indirectly, yes. The costs of the transmission grid are factored into the distribution system operators’ rates. The extent to which this occurs varies by grid area. The distribution system operators’ preliminary rate schedules will be published in October 2026, and the rates will take effect on January 1, 2027.
How does a single peak load affect grid costs?
With an annual capacity charge, the highest quarter-hourly demand measured during the year is multiplied by the capacity charge. A single peak, for example when several large loads start up at the same time, therefore sets the capacity component for the entire billing year, even if it never happens again.
Is a battery storage system worth it just for peak shaving?
Rarely. Organizational measures and the automatic curtailment of existing loads are more cost-effective and can be implemented more quickly. With the AgNes reform, the logic behind grid fees for industrial customers will change starting in 2029. A storage system should therefore also be factored in for self-consumption, load shifting, or emergency power.
The Next Step
torck operates Jouvoli as an ISO 50001-certified energy management platform that records load profiles, reports peaks and can curtail loads automatically. A pilot with existing meters and sensors takes six weeks. How measurement data from machines and meters comes together is described in the articles Energy monitoring in production, From Sensor to Dashboard and Implement Equipment Monitoring. Schedule an Initial Consultation.