Define Acceptance Criteria: How to Avoid Disputes After Go-Live

Defining Acceptance Criteria: How to Avoid Disputes After Go-Live

Acceptance criteria determine whether a software project will continue to run smoothly after go-live or end up in renegotiations. If you wait until the testing phase to define them, you’ll be negotiating from a weaker position.

Under German law governing contracts for work and services, acceptance marks the point at which the due date, the burden of proof, and the statute of limitations shift. Until that point, the contractor must prove that the software is free of defects; thereafter, this burden falls on the client. A specification without documented criteria pushes this point into a gray area where both parties have different expectations regarding the same contract.

Short answer

Clear acceptance criteria help prevent disputes after go-live if they are set forth in writing before the project begins, link each function to a verifiable test case, and distinguish between material and immaterial defects. A documented acceptance report (including the date, verified test cases, and identified remaining defects) provides the evidence that matters in the event of a dispute. In the absence of such criteria, the final decision often rests on a court’s interpretation of Section 640 of the German Civil Code (BGB), rather than on the intent of the contracting parties.

What Acceptance Means Legally and Why It Matters

Under Section 640 of the Civil Code, the customer is obligated to accept a work produced in accordance with the contract; the customer may not refuse acceptance on the grounds of minor defects (gesetze-im-internet.de, Section 640 of the German Civil Code (BGB)). Upon acceptance, payment becomes due, the burden of proof for defects shifts to the client, and for works involving manufacturing, maintenance, or modification, the two-year statute of limitations for defects begins to run. For typical custom software without this specific factual connection, however, the standard three-year statute of limitations under general provisions usually applies (gesetze-im-internet.de, Section 634a of the German Civil Code (BGB)). It begins at the end of the year in which the client becomes aware of the defect. Without documented criteria, it will be nearly impossible to determine later exactly what was considered to be in accordance with the contract.

Defining Acceptance Criteria: What Should Be Included in the Specifications

A robust criterion describes a result that can be verified using a test case, not a goal such as „intuitive operation“ or „modern user interface.“ Each function includes the expected sequence of events, acceptable response times, error handling for incorrect input, and responsibility for test data. Interfaces require their own criteria for data format, error handling, and the question of which party is responsible for a connected third-party system. This article describes how this information can be systematically incorporated into a requirements specification. Writing a Requirements Specification: A Guide with a Template. The more specific this list is before the project begins, the less room there is for interpretation later on.

Distinguish between functional and non-functional criteria

Functional criteria determine whether a feature does what was agreed upon, for example, whether an order is correctly entered into the inventory management system. Non-functional criteria pertain to characteristics such as load times, concurrent user counts, security requirements, and the scope of documentation. Both categories must be included in the requirements specification, because a court will only evaluate what was agreed upon in writing. If there is no specification regarding performance, the client cannot later claim that an application feels too slow if this expectation was not documented anywhere. The same applies to documentation, training, and data migration, three components of the service that are often taken for granted during negotiations and are therefore omitted from the contract text, until their absence becomes the actual point of contention after acceptance.

31 percent

According to the CHAOS Report, this is how many IT projects in 2022 were considered completely successful, completed on time and within budget with full functionality, while 19 percent were considered failures.

Standish Group, CHAOS Report, cited from sis-consulting.com, April 2026

How a Structured Acceptance Process Works

A professional process separates the technical testing from the legal acceptance. First, the agreed-upon test cases are run, the results are documented, and defects are classified by severity. The client then decides, based on predetermined criteria, whether to accept the work, accept it with reservations, or reject it due to material defects. If the client accepts the work despite a known defect, the client forfeits the right to claim for defects unless the client expressly reserves that right. In 2014, the Federal Court of Justice clarified that a confirmation of transfer alone does not constitute acceptance if it can be proven that key functions were not operational at that time (doctrine.de, Federal Court of Justice (BGH) VII ZR 276/13). A report that includes signatures, the date, and a list of remaining defects is therefore more than just a formality. In the event of a dispute, it is often the only document that both parties have signed together at the same time.

The Most Common Points of Dispute After Go-Live

In practice, most conflicts arise in the same areas. Change requests during development alter the scope of functionality without the acceptance criteria being updated accordingly. Partial acceptance tests for individual modules are missing, resulting in an “all-or-nothing” deadline for a complex system. And performance expectations remain verbal because both sides took them for granted. Those familiar with these three patterns can address them specifically in the requirements specification rather than discovering them only when a dispute arises. In a medium-sized project with a six-figure contract value, a single overlooked detail, such as the question of who provides test data for acceptance, is often enough to push back the planned go-live date by weeks. This article outlines where acceptance typically occurs in the course of a project and which phases precede it. The 7 Phases of a Software Project from the Client's Perspective one.

Checklist for a Rigorous Acceptance Test
Area What Must Be Documented
Features Test case for each core function with expected result
Interfaces Data Format, Error Handling, Responsibility
Performance Response times and maximum number of users
Defect Categories Definition of Material versus Non-Material
Minutes Date, Signature, Outstanding Defects
Where this approach reaches its limits
Even a precise requirements specification cannot prevent disputes over requirements that only become apparent during development, for example, because an integrated third-party system behaves differently than documented. In agile projects with a changing backlog, it is often impossible to clearly define a single acceptance date; instead, criteria for individual sprints or release stages are needed. Furthermore, legal interpretation remains a matter of case-by-case assessment, and a checklist is no substitute for a legal review when contract values are high.

Have the specifications reviewed before signing the contract
Those who wait until during development to refine acceptance criteria usually end up facing delays or having to renegotiate.

Get in touch

Frequently asked questions

Can the client refuse to accept the work due to minor defects?

No, according to Section 640(1) of the German Civil Code (BGB), acceptance cannot be refused due to minor defects. Whether a defect is material depends on the extent to which it restricts the agreed-upon use; an incorrect field name in a rarely used report is rarely considered material, whereas an incorrect price calculation in the ordering process almost always is. This is precisely why it is worthwhile to agree in advance on a definition of which error categories are considered material, rather than waiting to clarify this issue only when a dispute arises.

What happens if the client simply uses the software without formally accepting it?

Under Section 640(2) of the German Civil Code (BGB), a work is also deemed accepted if the contractor has set a reasonable deadline for acceptance after completion and the client does not report any defects within that period. In consumer contracts, this presumption applies only if a separate notice to that effect has been provided in writing. Actual use over a period of months without objection may also be regarded as tacit acceptance, even without an express declaration.

Should acceptance criteria also be defined for agile projects?

Yes, even in agile development, a focus on success remains useful if verifiable interim results or release milestones have been agreed upon. Instead of a single acceptance meeting at the end of the project, it is recommended to conduct an acceptance review after each sprint or release, following the same basic rules regarding test cases, documentation, and the distinction between material and immaterial defects. If this performance-based framework is completely absent and work is performed solely on a time-and-materials basis without any guarantee of success, courts sometimes tend to classify such contracts as service contracts, which have their own rules regarding defects, termination, and compensation.

torck establishes acceptance criteria for custom software projects before the contract is signed and uses them as a working basis for development and testing. Because the development team helps create the criteria that it will later have to meet, they remain both technically feasible and legally sound. For more information on the process for custom software development, visit the page Custom Software Development.

Schedule a meeting

Legal note
This article discusses legislation and regulations as context for technical decisions. It does not constitute legal advice. Consult your legal team or external counsel about whether and how a particular rule applies to your organisation.

Questions about this post?

Two sentences about your situation are enough. You’ll hear back from someone who builds systems like these themselves.

We'll respond within one business day.torck · Code mit Drehmoment
Florian Blischke
Managing Director at torck · Over 20 years of software development experience
Florian Blischke is the managing director of torck, based in Maxhütte-Haidhof near Regensburg. He has been working in software development for over 20 years. His focus is custom software, data and AI for industry and retail, ranging from the integration of physical processes and IoT to cloud architecture and data- and AI-driven systems. torck works with its own nearshore team in Rabat. At torck, he oversees projects including the Jouvoli energy platform and the KVM Fleet fleet management product. torck develops software at its locations in Maxhütte-Haidhof, Vienna and Rabat and focuses on software that actually works in operation.

Are you facing the same question?

Since 2017, we have been building software for industry and retail from Maxhütte-Haidhof near Regensburg, with teams in Vienna and Rabat. An initial consultation takes 30 minutes and costs nothing. Afterwards you will know whether the project is worth pursuing, even if the answer is no.

More Articles

Cybersecurity requirements under the EU Machinery Regulation: What machine builders must do by January 20, 2027, regarding control software, updates, and change logs.

EU Machinery Regulation cybersecurity requirements: what machine builders must do by 20 January 2027 for control software, updates and change logs.

Starting January 20, 2027, new machines must be protected against corruption in accordance with Annex III of the Machinery Regulation. Regulatory authorities must be able to access a log documenting interventions and versions of the safety software for up to five years. A model calculation illustrates the costs associated with the control system, HMI, and remote maintenance. Four approaches are viable options by the deadline.

Read more »
Replacing SAP ECC: When to choose another ERP system, when to extend maintenance through 2030, and when upgrading the systems surrounding ECC is sufficient.

Replacing SAP ECC: when to choose another ERP system, when to extend maintenance through 2030 and when upgrading the systems around ECC is enough.

SAP offers extended maintenance for ECC through the end of 2030 at a rate two percentage points above the standard rate. The extension covers every system under the agreement. Customers must sign the addendum before the end of 2027. We compare the work, costs and risks of moving to S/4HANA, implementing a different ERP system, extending maintenance or separating the systems that run alongside ECC.

Read more »
AI Funding in Austria: Programs and Deadlines for 2026

AI Funding in Austria: Programs and Deadlines for 2026

Two time-limited programs for AI projects in Austria will be open through the end of 2026: “Industrial AI Upper Austria” for Upper Austrian consortia through December 10, and the “Vienna Digitalization Grant” through December 31. The FFG Basic Program, which accepts applications on any topic, accepts applications at any time. The KMU.DIGITAL budget has been exhausted. The overview shows which funding program is best suited for each project.

Read more »